Power Is the Next Bottleneck After Nvidia, Part 1: Why GPUs Alone Cannot Turn a Data Center On

Buying GPUs does not help if a data center cannot get power. See AI power demand forecasts, Big Tech capex, grid bottleneck evidence and a supply chain map.

On this page

Aerial photo of data center buildings clustered around Ashburn, Virginia, with a large electrical substation in the foreground. The area is regarded as the world's largest data center cluster

Photo: Theodore Christopher, CC0, via Wikimedia Commons

AI power infrastructure is all the equipment that generates, transmits and distributes electricity to AI data centers. It covers power plants, transmission lines and transformers, the switchgear and uninterruptible power supplies (UPS) inside the data center, and energy storage systems (ESS). For the past three years, AI investment has centered on Nvidia GPUs. The next question for investors is whether there is enough electricity to run them.

A data center cannot operate on GPUs alone. If the power supply falls short, the chips sit idle. That is why rising data center demand lifts spending on power plants, gas turbines, transformers, transmission grids and storage together. Part 1 uses primary-source figures to show how Big Tech executives talk about power, how fast demand is expected to grow and what evidence shows the grid falling behind. It then maps which companies sit at each stage of the power supply chain.

Power Is the Next Bottleneck After Nvidia series. Part 1: Why power is AI's bottleneck · Part 2: Generation (gas turbines, nuclear) · Part 3: Transformers, transmission, cables · Part 4: Distribution, data-center power, storage · Part 5: Is power a better investment than chips?

Why a Data Center Cannot Run on GPUs Alone

A data center needs more than servers. Servers can only be installed in a building that has power and cooling, and that building must be connected to the grid before it can operate. An AI server rack draws far more power than a conventional one, so securing electricity has become slower than securing chips.

Big Tech executives have said so directly. Microsoft CEO Satya Nadella said on the BG2 podcast, released in November 2025, that the biggest issue now is not a compute glut but power. He said chips could sit in inventory that cannot be plugged in, and that he does not have "warm shells" (empty buildings with power and cooling in place) to plug them into (TechCrunch, Nov 3, 2025).

Amazon CEO Andy Jassy named power AWS's "biggest constraint" on its Q2 2025 earnings call. In July 2026 he said Amazon would not secure enough capacity to meet all demand in 2026 or in 2027. Nvidia CEO Jensen Huang said on the August 2026 earnings call that securing land, power and buildings typically takes two to three years.

A data center hall full of server racks where only some are lit because the incoming power lines are thin, showing that GPUs cannot run without power

How Much Will Data Center Power Demand Grow?

The most cited forecast is the International Energy Agency (IEA) report "Energy and AI," published in April 2025. The IEA estimated that data centers worldwide used 415 TWh in 2024, about 1.5% of global electricity consumption, and that demand would more than double to about 945 TWh by 2030 in its base case. That is slightly more than Japan's total electricity consumption today. In a June 2026 release, the IEA said data center electricity demand grew by nearly 20% in 2025, and that bottlenecks in energy and technology supply chains leave its 2030 outlook close to the earlier path.

The share is larger in the US alone.

Source (date)ScopeCurrentForecast
IEA, "Energy and AI" (Apr 2025)Global data centers415 TWh in 2024 (about 1.5% of electricity use)About 945 TWh in 2030, about 1,200 TWh in 2035
Lawrence Berkeley National Laboratory / US Department of Energy (Dec 2024)US data centers176 TWh in 2023 (about 4.4% of US electricity)6.7-12% of US electricity in 2028
Electric Power Research Institute (EPRI, 2026)US data centers4-5% of US electricity9-17% in 2030
Grid Strategies (Nov 2025)Peak demand in US utility forecastsFive-year growth forecast of 24 GW (three years earlier)Growth forecast of 166 GW through 2030

The IEA expects data centers to account for nearly half of US electricity demand growth through 2030, and US data center consumption to exceed that of aluminum, steel, cement and chemicals combined. The range of forecasts is wide, though. The IEA's 2035 scenarios span 700-1,720 TWh, a gap of more than double, and Grid Strategies judged that data center demand in utility forecasts is likely overstated by about 25 GW.

Big Tech Capex Becomes Power Demand

Data center power demand starts with Big Tech capital spending. Based on the Q2 2026 earnings releases, the four companies' 2026 spending plans are about double their 2025 actuals.

Company2025 actual2026 plan (as of July 2026)
AmazonAMZN$128.3 billionAbout $220 billion
AlphabetGOOGL$91.4 billion$195-205 billion
MetaMETA$69.7 billion$130-145 billion
MicrosoftMSFT$64.6 billion (fiscal 2025, year ended June 2025)About $175 billion (2026 basis, reflecting a lease accounting change)

Each company defines capex differently (cash spending, whether finance leases are included) and uses a different fiscal year, so the figures should not be added up. Source: each company's Q2 2026 earnings call transcript and press release

In its June 2026 release, the IEA noted that capex at the five largest technology companies had already surpassed global investment in oil and gas production. A large share of that money goes to servers and data center buildings, and every one of those buildings is waiting for electricity.

Evidence That the Grid Cannot Keep Up

Reuters columnist Ron Bousso laid out this bottleneck in a February 25, 2026 column titled "US AI boom faces electric shock." As of December 2025, 226 GW of large loads, mostly data centers, had applied to connect to the grid run by Texas operator ERCOT. GE Vernova and Siemens Energy executives said gas turbines are "sold out for years," and 46 data centers were planning their own power plants totaling 56 GW.

The numbers grew after that. ERCOT's queue of large loads waiting to connect reached 474.7 GW in June 2026, more than five times the state's all-time peak demand of 91 GW (July 22, 2026) (POWER, Aug 4, 2026). Many of those requests are duplicates, with the same project filed in several places, and ERCOT's market monitor said the figure should be treated as an upper bound.

Capacity market prices at PJM, the largest US grid operator, show the supply shortfall more directly. A capacity market is an auction that pays power plants in advance for committing to supply electricity several years out.

Delivery yearCapacity price (per MW-day)Notes
2024/25$28.92
2025/26$269.92About 9.3 times the prior year
2026/27$329.17Hit the price cap
2027/28$333.44At the cap; 6,516.6 MW short of the reliability requirement
2028/29$325At the cap; 6,831 MW short, the first time in PJM history that the whole footprint fell short

Source: PJM 2027/28 capacity auction report (Dec 17, 2025); PJM press release on 2028/29 auction results (Jul 14, 2026)

PJM CEO David Mills said electricity demand is growing faster than supply. The IEA also found that about 20% of planned data center projects could be delayed by grid constraints, that building a new transmission line in advanced economies takes four to eight years, and that lead times for transformers and cables have doubled in the past three years.

Chart data

Chart summary: Vistra (VST) daily candles, 2024-01-02 to 2026-10-09. Close 38.07 USD → 161.48 USD (+324.2%); period high 219.82 (2025-09-22), low 37.77 (2024-01-03). Marked: PJM price spike 2024-07-31 close 79.22, DeepSeek shock 2025-01-27 close 137.08, Meta nuclear 2026-01-09 close 166.37.

The share price of Vistra, a US power producer, tracked this supply and demand picture closely. Vistra owns gas and nuclear plants in Texas and the PJM region, and it sells electricity and capacity at higher prices when power is scarce. As the chart shows, the stock rose sharply after PJM capacity prices spiked in 2024, but it fell 28.3% in a single day on January 27, 2025, when investors doubted AI power demand.

Power Supply Chain Map: Which Companies Sit at Each Stage

The path electricity takes to a data center breaks into five stages. Power plants generate the electricity, transmission grids carry it long distances at high voltage, substations step the voltage down, distribution networks and in-building equipment divide it up, and UPS and ESS guard against outages and surges. Each stage is a different industry with different companies.

The path of electricity from power plant through transmission lines, substations and distribution network to the server racks in a data center. If any one stage is blocked, the whole data center cannot operate

StageWhat it doesRepresentative companiesCovered in
GenerationProduces electricity with gas turbines, nuclear and fuel cellsGE Vernova, Siemens Energy, Mitsubishi Heavy Industries, Doosan Enerbility, Constellation, VistraPart 2
Transmission and substationsSends power at high voltage and changes voltage with transformersHD Hyundai Electric, Hyosung Heavy Industries, Hitachi Energy, LS Cable & System, Taihan Cable, PrysmianPart 3
DistributionDivides and protects power with switchgear, breakers and distribution panelsLS ELECTRIC, Eaton, Schneider Electric, ABBPart 4
Power inside the data centerDelivers electricity to server racks through UPS, PDUs and power suppliesVertiv, Eaton, Schneider ElectricPart 4
Storage (ESS)Uses batteries to cover outages and absorb load swingsTesla, Fluence, LG Energy Solution, Samsung SDIPart 4

What matters in this table is that the slowest stage sets the pace for the whole chain. If gas turbines take three to five years, large transformers two to five years and transmission lines four to eight years, a data center turns on only after those are done, even if the GPUs arrive in a few months. The market has therefore sorted companies by which stage has been blocked the longest.

Korea Faces the Same Problem

Korean data centers are also queuing for power. According to Dong-A Ilbo, of 290 data center power supply applications received by Korea Electric Power Corporation (KEPCO) between August 2024 and June 2025, 195 (67%) were in the Seoul metropolitan area, totaling about 20 GW, the equivalent of 20 nuclear reactors. Only four of 19 metropolitan-area projects passed the government's grid impact assessment (Jul 30, 2025).

Supply conditions are also unfavorable. In 2024, the Seoul metropolitan area generated 66% of the power it used, and Seoul only 11.6% (Financial News, Jan 5, 2026). According to Hankyung, the government's draft 12th Basic Plan for Electricity Supply and Demand sets 2040 data center demand at 26.5 TWh, 1.7 times the 2038 forecast of 15.5 TWh in the 11th plan (Jun 25, 2026). This is why Korea's bigger problem is the transmission grid and regional allocation rather than power plants.

The Limits of This Story: Demand Forecasts Can Be Overstated

First, power demand forecasts include duplicates and speculation. ERCOT's queue (474.7 GW) is more than five times the state's peak demand, and Grid Strategies judged that data center demand is inflated by about 25 GW. A connection request costs almost nothing, while actual construction costs real money, so the share of requests that turn into real demand may be low.

Second, efficiency can reduce demand. The IEA puts 2030 data center demand at about 800 TWh if efficiency improves sharply and about 670 TWh if investment slows, well below the base case of 945 TWh. This doubt is also why power stocks fell 20-28% in a single day in January 2025, when DeepSeek released an AI model built with less compute.

Third, all of this demand depends on Big Tech spending. Record 2026 spending plans also mean that if investment shrinks, power demand forecasts could be cut with it. Part 5 returns to this question by comparing power with semiconductors.

Checkpoints for Investors

  • Do you know which institution and which scenario a data center power forecast comes from, and have you checked the base, optimistic and pessimistic range?
  • Did Big Tech capex guidance rise or fall this quarter, and have you allowed for the fact that each company defines it differently?
  • How much of the grid connection queue is turning into actual power supply contracts?
  • Are capacity market prices such as PJM's still hitting the cap, or is the shortage easing?
  • Have you noted which stage of the power supply chain the company sits in and how long the lead time at that stage is?

Frequently Asked Questions

Q1. How much electricity does a 1 GW data center use?

1 GW is about the output of one nuclear reactor. The Reuters column explained that the largest US data centers use more than 1 GW, enough to supply up to 850,000 homes.

On an annual basis, Korean industry sources estimate that one 1 GW AI data center adds 6-7 TWh of consumption per year (Hankyung, Jun 25, 2026). Actual usage depends on utilization and the cooling method, so "1 GW = one reactor's output" is best used only as a rough sense of scale.

Key Takeaways

  • AI power infrastructure is the whole supply chain running from generation to transmission and substations, distribution, power inside the data center and ESS, and the slowest stage sets when a data center can go live.
  • Nadella, Jassy and Jensen Huang each named securing power and buildings as a constraint on AI expansion.
  • The IEA expects global data center electricity use to grow from 415 TWh in 2024 to about 945 TWh in 2030, and US data centers are projected at 6.7-12% of US electricity in 2028.
  • PJM capacity prices rose from $28.92 in 2024/25 to $325 (the cap) in 2028/29, and for the first time the whole footprint fell short of the reliability requirement.
  • Korea's metropolitan data center power applications total about 20 GW, while Seoul generates only 11.6% of the power it uses.
  • Demand forecasts carry downside factors such as duplicate requests, efficiency gains and slower Big Tech investment, so they are best read as a range of scenarios.

References

  • IEA, "Energy and AI" (World Energy Outlook Special Report, Apr 2025)
  • IEA, "Key questions on energy and AI" (release, Jun 11, 2026)
  • Lawrence Berkeley National Laboratory / US Department of Energy, "2024 United States Data Center Energy Usage Report" (Dec 2024)
  • EPRI, "Powering Intelligence 2026: Updated Scenarios of U.S. Data Center Electricity Use and Power Strategies" (2026)
  • Grid Strategies, "Power Demand Forecasts Revised Up for Third Year Running, Led by Data Centers" (Nov 2025)
  • TechCrunch, "Altman and Nadella need more power for AI, but they're not sure how much" (Nov 3, 2025)
  • Latitude Media, "Power is AWS' single biggest constraint" (Aug 5, 2025)
  • Amazon and Microsoft Q2 2026 earnings call transcripts (posted by The Motley Fool, Aug 7, 2026)
  • Nvidia fiscal 2027 Q2 earnings call transcript (Aug 26, 2026)
  • Reuters, Ron Bousso, "US AI boom faces electric shock" (column, Feb 25, 2026)
  • POWER Magazine, "Abbott orders full audit of Texas data center interconnection queue" (Aug 4, 2026)
  • PJM, "2027/2028 Base Residual Auction Report" (Dec 17, 2025); press release on 2028/2029 auction results (Jul 14, 2026)
  • W.Media, StorageNewsletter, MLQ.ai, reports on Big Tech 2026 capex guidance (Jul 2026)
  • Dong-A Ilbo, report on data center power supply applications concentrated in the Seoul metropolitan area (Jul 30, 2025)
  • Financial News, report on metropolitan-area power self-sufficiency and AI data center capacity (Jan 5, 2026)
  • Hankyung, report on data center demand in the 12th Basic Plan for Electricity Supply and Demand (Jun 25, 2026)
  • Stock prices: Alpaca daily bar data (calculated on closing prices)

For reference only: The information in this post is provided for general reference and does not constitute investment advice or a solicitation to trade. Your responsibility: Final investment decisions and their outcomes are entirely your own. No warranty: This information is not guaranteed to be accurate and cannot be used as a basis for legal liability for any investment result.

Trading review workflow

Turn this read into your next trading review

Capture the chart, thesis, mistakes, and next improvement in one review flow so the lesson stays usable.

Start a trading journal

Market context is provided for research and review, not personalized financial advice.